New Detached ADU in Burbank: What It Costs and How Long It Takes
A new detached ADU in Burbank typically runs $90,000 – $220,000 and takes 8 – 12 months from first drawing to final inspection, with the bulk of that time spent in plan check and construction rather than design. A detached unit is a separate structure with its own foundation, utilities, and address, so it costs more than a garage conversion but adds real living space without touching your main house. For a written line-item estimate on your lot, call (844) 797-7958.
The five stages a detached unit actually moves through

Most homeowners underestimate the front half of this project. Design and permitting eat as much calendar time as the build itself, and the decisions you make early lock in what the later stages cost.
Stage 1: Site check and feasibility (1 – 2 weeks)
We walk the lot and measure setbacks, identify where the sewer lateral and main electrical panel sit, and confirm what your zoning allows for a second dwelling. In Burbank you also need to know how much of the lot is buildable after fire-clearance and hillside rules apply. You decide here whether the unit goes in the back yard, off the alley, or over an existing pad.
Stage 2: Design and plan check (3 – 6 months)
Drawings get prepared, then submitted to the city for plan check. Burbank’s building department returns comments, the designer revises, and you resubmit. This back-and-forth is normal and can add weeks. You approve the floor plan, the exterior finish, and whether power and gas come from the main house or get separate meters.
Stage 3: Site prep and foundation (3 – 5 weeks)
Grading, trenching for utilities, and pouring the slab or stem-wall foundation. If your lot slopes, retaining and drainage work lands here. On hillside lots above the valley floor, fire-clearance requirements shape where equipment can stage. You sign off on utility routes before trenches get backfilled.
Stage 4: Framing, rough-in, and envelope (8 – 12 weeks)
Walls go up, then plumbing, electrical, and HVAC rough-in get inspected before the walls close. Roofing, siding, and windows follow. This is the stage where material choices become visible, so you want your finish selections locked before framing finishes.
Stage 5: Finishes and final inspection (6 – 10 weeks)
Drywall, cabinets, counters, flooring, fixtures, paint. Then the final inspection and a punch walk with you. We don’t call a job done until the city signs off and you’ve walked it. Everything we finish carries our 730-Day Done Right Promise.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll actually choose between
- Slab-on-grade vs. raised floor. A slab is cheaper and simpler on flat lots; a raised floor suits sloped or hillside lots and runs higher. Slab suits most flatland Burbank lots.
- Siding: James Hardie fiber cement vs. stucco. Fiber cement holds paint longer and handles heat well; stucco matches the Spanish Revival look common in Magnolia Park. Both are solid; pick for looks and maintenance appetite.
- Cabinets: KraftMaid vs. Wellborn. Both are quality lines with different door styles and price points. A small kitchenette setup keeps cost down; a full kitchen pushes the number up.
- Attached utilities vs. separate meters. Tapping the main house is cheaper up front; separate meters cost more but make the unit easier to rent or pass to family.
- Prefab shell vs. stick-built. A prefab shell can save weeks on framing but limits custom layouts. Stick-built gives full flexibility for the cost of more labor.
What a New Detached ADU costs in Burbank, CA

Expect $90,000 – $220,000 for a detached unit here. The low end reflects a compact one-bedroom on a flat lot with utilities tapped from the main house and standard finishes. The high end reflects a two-bedroom with a full kitchen, separate meters, upgraded siding, and site work on a sloped or tight lot.
Four things move the number most:
- Size and bedroom count. Every additional bedroom and bathroom adds plumbing runs, fixtures, and square footage.
- Site conditions. Slope, drainage, and utility distance all add labor before a wall goes up.
- Utility strategy. Separate meters and a new panel cost more than tapping existing service.
- Finish grade. Standard cabinets and flooring vs. upgraded lines swing the total meaningfully.
A written estimate spells out foundation, framing, utilities, finishes, and permit fees line by line. What it typically excludes: city plan-check fees paid directly, any soil or engineering reports the city requires, and landscaping beyond basic grading. You get the number up front and it doesn’t change once work starts.
See the difference
Before
After
Before
After
Before
AfterWhat Burbank homes specifically do to this job
Burbank’s housing stock changes how a detached unit gets built. In Magnolia Park and the Rancho Equestrian district, the 1920s – 40s bungalows often sit on lots with older utility runs and hidden unpermitted work that surfaces the moment a permit gets pulled. We plan for that. Hillside streets above the valley floor face some of the tightest fire-clearance and grading scrutiny in the region, so a sloped lot needs drainage and clearance designed in from the start, not added later. The dry valley heat and Santa Ana wind events push hard on exterior finishes, which is why we favor materials that hold up to heat and sun on unshaded walls. This is part of the wider Home Additions & ADU in Burbank scope, and homeowners often pair the new unit with Concrete Driveways & Concrete Work in Burbank for a proper parking pad. Some also add Paver Driveways in Burbank for the approach.
Serving Burbank, CA – Our Local Coverage Area
We serve Burbank and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – New Detached ADU in Burbank

Plan on 8 – 12 months total, with 3 – 6 of those months in design and plan check before any construction starts. The build itself usually runs 5 – 7 months. Call (844) 797-7958 for a timeline based on your specific lot.
Yes. A detached unit requires full building permits and inspections, and the city reviews plans before work begins. We handle the permit process and inspections as part of the job, so the unit is legal and insurable when it’s done.
In most cases, yes. A detached unit has its own foundation and utilities, so it usually doesn’t disturb the main house structure. The main decision is whether to tap existing service or add separate meters, which affects cost but not the house itself.
Most projects land between $90,000 and $220,000 depending on size, site, and finishes. Call (844) 797-7958 for an exact quote built as a line-item written estimate, and estimates are free.
Every project is covered by our 730-Day Done Right Promise. If something isn’t done right, we make it right. That’s backed in writing, and we stand behind it after the final inspection.
Get a Written Estimate for Your Detached Unit
A detached unit is a big commitment, and you deserve a real number before you commit. Call (844) 797-7958 for a free on-site estimate for your New Detached ADU in Burbank. We’ll walk the lot, measure setbacks, and talk through what your property allows. From there you get a line-item written estimate with the price locked in. Part of our Home Additions & ADU work across Burbank.
Written by the team at Groundwork Construction Co.