ADU Site Prep & Utilities in Burbank: What It Takes Before You Build
ADU site prep and utilities in Burbank runs $45,000 – $130,000 and typically takes six to ten weeks on site before any framing goes up, covering demolition, grading, the trench for water, sewer and gas, the electrical service upgrade and the concrete slab. This is the work that has to pass inspection before a single wall gets built. Call (844) 797-7958 for a free on-site estimate and a line-item quote written the day we walk the lot.
How Our ADU Site Prep and Utility Work Moves, Stage by Stage

We break the job into five stages. You’ll know which one you’re in, what the inspector looks at, and what you need to decide before we move to the next.
Stage 1 – Site walk and utility locate (day 1 to 3). We call in DigAlert, mark the existing water, sewer and electrical laterals, and flag anything that sits where the foundation needs to go. You decide the pad location and which side the service entry arrives from. Timing here depends on how fast the locates come back, usually two to three business days.
Stage 2 – Demolition and clearing (day 3 to 7). Old concrete, sheds, fences, tree stumps and the aging driveway come out. On Magnolia Park and Rancho Equestrian lots this is also where the surprises surface, because those 1920s – 40s properties often hide a converted garage or a rear addition that never pulled a permit. You need to know now whether that extra square footage is legal in the city’s eyes.
Stage 3 – Trenching and rough utilities (day 7 to 25). Trenching for the sewer line to the main, the water supply, gas and the electrical conduit. If your existing 100-amp service needs an upgrade to 200-amp, that happens here, and it’s often the single biggest line item. You sign off on the fixture locations and outlet layout before the trench closes.
Stage 4 – Grading, drainage and slab (day 25 to 42). We grade to the finished pad elevation, set drainage that anticipates both the summer dry-out and the winter runoff the Verdugo slope throws at you, and pour the slab. A hillside pad needs retaining and fire-clearance grading the flatland pad doesn’t.
Stage 5 – Inspections and rough-in sign-off (day 42 to 60-plus). Burbank’s building department inspects the grade, the underground plumbing and the electrical before you close up. This is where a job either stays on schedule or slips. We don’t frame until those sign-offs land.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Be Making on Site Prep
Site prep isn’t glamorous, but the specs you pick here decide whether the ADU is easy to finish and easy to maintain. Here’s what actually comes up:
- Pad type – concrete slab vs. raised foundation or pier-and-beam. A slab is faster and cheaper to prep and works on a level lot. A raised floor handles the Verdugo slope better and keeps plumbing accessible, but it adds grading, framing and cost.
- Utility route – direct trench vs. long lateral to the main. Short runs to a nearby sewer main are cheap. If your lot is deep or the main sits across a road, the lateral and its trenching can double the utility cost.
- Electrical service – upgrade vs. existing. Older Burbank homes often carry 100-amp service that won’t absorb an ADU’s load. A 200-amp upgrade is sometimes unavoidable and worth planning for upfront.
- Grading and drainage. Flat lots need simple surface drainage. Hillside lots need retaining walls, swales and fire-clearance grading, which adds weeks and real dollars.
- Siding and finish on the shell. James Hardie fiber cement holds up to Valley heat and dry summers without the moisture trapping older wood siding deals with. It’s the practical spec for a Burbank ADU.
What ADU Site Prep & Utilities Costs in Burbank, CA

Expect $45,000 – $130,000 for the prep and utility scope alone, with $45,000 – $70,000 landing on a simple flat-lot pad with short runs, and jobs north of $100,000 tied to hillside grading, long laterals or an electrical service upgrade. The full ADU build itself is a separate number; see our Home Additions & ADU in Burbank page for the wider project, or our Home Additions & ADU hub for the broader scope.
| Line item | Typical range |
|---|---|
| Site clearing and demolition | $3,000 – $12,000 |
| Trenching and underground water, sewer, gas | $8,000 – $30,000 |
| Electrical service upgrade (100 to 200-amp) | $4,000 – $12,000 |
| Grading, drainage and concrete slab | $18,000 – $45,000 |
| Hillside retaining and fire-clearance grading | $10,000 – $30,000 |
What moves the number. Bad existing conditions (unpermitted structures, old laterals, rock in the trench) push jobs to the high end. A short direct utility run and a clean flat pad keep it low. Grading complexity on a slope is the single biggest swing. So is whether the electrical service needs an upgrade. A written estimate covers demolition, trenching, grading, slab and inspection coordination. It won’t cover surprises underground or a permit that uncovers an illegal addition.
See the difference
Before
After
Before
After
Before
AfterWhat Burbank Homes Do to This Job
Burbank runs a hot, dry Valley-basin climate with Santa Ana wind events pushing fire risk to the Verdugo hillside edges. That shape shows up directly in site prep: hillside lots above the valley floor need fire-clearance grading and drainage built to handle flash runoff, and the city’s hillside grading review is tight. On the flatland, our Magnolia Park and Rancho Equestrian jobs routinely surface old unpermitted additions or converted garages the moment a permit gets pulled, so the locate and demo stages expose problems early. Many of those 1920s – 40s Spanish Revival and Craftsman homes carry original knob-and-tube wiring and lath-and-plaster walls, which affects how we tie the new service in. If you’re reworking the driveway as part of the same project, homeowners often pair this with Concrete Driveways & Concrete Work in Burbank or Paver Driveways in Burbank while the equipment is already on site. We cover Burbank and the surrounding foothill communities.
Serving Burbank, CA – Our Local Coverage Area
We serve Burbank and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – ADU Site Prep & Utilities in Burbank

Six to ten weeks on site before framing, and hillside jobs with heavy grading can run longer. Inspection scheduling at the Burbank building department is the main variable once the trench is in. Call (844) 797-7958 for a timeline on your specific lot.
Yes. Grading, underground plumbing and the electrical service upgrade all get inspected, and the ADU permit itself can’t proceed without the sign-offs. We coordinate Burbank’s building department reviews so you’re not the one chasing them.
Sometimes. A clean flat lot with a nearby sewer main and adequate electrical can prep with minimal disruption. Older homes with unpermitted additions or 100-amp service usually can’t, and we’ll tell you which you’re in after the site walk.
Underground surprises (rock, old laterals, illegal structures) can change the number. We surface those risks in the written estimate and quote the line items upfront so there’s nothing hidden. Call (844) 797-7958 for a firm quote.
Our site prep and utility scope carries the 730-Day Done Right Promise. If it’s not done right, we make it right, in writing. The number you see on the estimate is the number you pay.
Get Your Free On-Site Estimate in Burbank
Site prep is where the budget gets locked and the schedule gets set, so it pays to get the number right the first time. We walk the lot, mark the utilities, and hand you a written line-item estimate covering demo, trenching and grading, so you know exactly what you’re spending before the first shovel hits dirt. Call (844) 797-7958 for a free on-site estimate in Burbank.