Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled
Garage Conversion ADU in Burbank: What It Costs and How Long It Takes
A garage conversion ADU in Burbank runs $45,000 to $130,000 and typically takes four to seven months from first permit submittal to final inspection. The garage shell already exists, which is why this is the cheapest route to a rentable unit on your lot. You’re adding a floor, insulation, plumbing, electrical, HVAC, windows, and a kitchen and bath inside a box that’s already standing. Call (844) 797-7958 and we’ll walk your garage and give you a written, line-item number before anything gets moved.
How a Garage Conversion ADU Comes Together, Stage by Stage

People ask what actually happens week to week, so here’s the honest sequence. Not every job hits these timings exactly, but this is the shape of it.
Stage 1 – Feasibility and design, weeks 1 to 4. We measure the garage, check the slab, look at ceiling height and how the roof is framed, and confirm the setback and lot-coverage math for a habitable unit. You decide the layout here: studio versus one-bedroom, where the kitchenette lands, whether the bath goes on the alley wall or the house wall. That bath placement matters more than anything else, because it decides how far we’re trenching for the drain.
Stage 2 – Permits, weeks 3 to 10. Plans go to the city and come back with comments. Burbank’s plan check is thorough, and seismic and life-safety review is a real step here, not a formality. You sign off on the plan set and pay permit fees at this stage. We handle the submittal and the comment responses.
Stage 3 – Demo and shell work, days 1 to 10 of construction. The door comes off and gets framed in. We strip anything that has to go, pour or level the slab where needed, and frame interior walls. Rough plumbing and electrical go in after framing, and that’s the point where we open the walls and see what the garage was hiding.
Stage 4 – Rough-in inspections and close-up, weeks 4 to 9. Framing, plumbing, electrical, and mechanical inspections happen in sequence. Once they pass, insulation goes in, then drywall. You pick fixtures, tile, and cabinet finishes in this window so nothing sits waiting on a decision.
Stage 5 – Finish and final, weeks 9 to 16. Flooring, paint, cabinets, countertops, bath fixtures, HVAC trim, and a kitchenette hookup. Final inspection, then a walkthrough with you. That’s where the ADU becomes a signed-off, rentable unit rather than a finished-looking garage.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Actually Shape Your Garage Conversion ADU
Most of the money and most of the arguments live in four or five decisions. Here’s how we frame them for homeowners.
- Slab versus raised floor. A garage slab is usually close to grade, which means moisture. We either seal and insulate over the existing slab or build a shallow raised floor. The raised floor costs more but keeps carpet and cabinets dry during winter rain and gives us room to run plumbing underfoot.
- Bath placement. A bath near the existing house wall lets us tie into the main drain with a short run. Moving it to the far corner adds trenching, a new vent stack, and real money. This single choice can swing a job by several thousand dollars.
- Kitchenette grade. You’re choosing between a compact all-in-one unit and a full cabinet run. KraftMaid and Wellborn both make compact lines that hold up to tenant use and keep the kitchenette under about 8 feet of wall. Cheaper box-store cabinets look fine on day one and don’t survive a rental turnover.
- Exterior skin. Most Burbank garages are stucco, and matching old stucco is fussy. James Hardie siding on the converted face gives a clean, fire-resistant finish that reads as intentional next to the house and doesn’t fight the original stucco texture.
- HVAC approach. A ductless mini-split is the common pick for a single-room conversion and runs cheaper than extending the house system. If you’re planning to rent the unit out separately, a dedicated meter and its own system make the utility split simple.
What a Garage Conversion ADU Costs in Burbank, CA

Plan on $45,000 to $130,000 for a garage conversion ADU in Burbank. The low end is a studio with a kitchenette, a compact bath near the house wall, and modest finishes. The high end is a one-bedroom with a full kitchen, upgraded tile and cabinets, new HVAC, and structural work to bring an older garage up to habitable standards.
Four things push the number up or down:
- Existing garage condition. A dry, level slab and a sound roof keep you at the low end. A cracked slab, a sagging header, or a roof that needs replacing before we insulate adds cost fast.
- Plumbing and electrical distance. The farther the bath and kitchenette sit from the house’s existing service, the more trenching and panel work you’re paying for.
- Panel capacity. Many older Burbank garages are fed by a single circuit. A conversion needs its own circuits and often a panel upgrade, which is a real line item.
- Finish grade. Flooring, tile, and cabinet choices move the total by thousands. We quote them as separate line items so you can see exactly what each upgrade costs.
- Permit and inspection scope. Fire separation, seismic tie-downs, and energy compliance all add scope that a detached new build sometimes avoids.
A written estimate from us breaks out demo, framing, rough trades, insulation, finishes, permits, and inspections as separate lines. What it won’t include is furniture, appliances if you’re supplying your own, or landscaping once the unit is done. Everything we quote is fixed, so the number you sign is the number you pay. If it’s part of a full Home Additions & ADU in Burbank plan, we scope the two together so nothing gets built twice.
See the difference
Before
After
Before
After
Before
AfterWhat Burbank Garages Specifically Do to This Job
Burbank’s housing stock makes garage conversions here a different animal than in a newer tract suburb. In Magnolia Park, we routinely open up a 1930s or 1940s bungalow’s garage and find knob-and-tube wiring, lath-and-plaster walls the previous owner skimmed over, and a converted space that was never permitted in the first place. That last part matters: the city will want the unpermitted work either legalized or removed before it signs off on an ADU, so we plan for it up front instead of discovering it mid-job.
Out in the Rancho Equestrian district, garages are often larger and tied to tack rooms or storage, and the conversion has to work around horse-property setbacks and the way those lots drain. Up in the Verdugo foothills and the hillside streets above the valley floor, fire-clearance and hillside grading review is tighter than in most of the region, and a garage conversion there has to satisfy that scrutiny before it satisfies anything else. The dry San Fernando Valley heat is hard on unshaded garage roofs and stucco, so we check roof condition and insulation before we close anything up. If you’re covering the driveway approach at the same time, homeowners often pair this with Concrete Driveways & Concrete Work in Burbank.
Serving Burbank, CA – Our Local Coverage Area
We serve Burbank and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Burbank

Most take four to seven months from permit submittal to final inspection. Plan check on its own can run six to ten weeks in Burbank, and construction is typically another ten to sixteen weeks depending on how much the existing garage surprises us. Call (844) 797-7958 and we’ll give you a realistic timeline for your specific garage.
Yes. A habitable ADU requires building, electrical, plumbing, and mechanical permits, plus inspections at each stage. Skipping them creates a unit you can’t legally rent and a headache when you sell. The local pro we connect you with is licensed and insured as their state requires and pulls the permits before work starts. Call (844) 797-7958 to talk through your permit situation.
Often, yes, if the bath and kitchenette land near where the house’s existing drain and panel already are. Putting the bath on the wall shared with the house keeps trenching short and usually avoids structural changes. Turning the garage into something the plan doesn’t support is where cost climbs. Call (844) 797-7958 and we’ll tell you which side of that line your garage is on.
Between $45,000 and $130,000, depending on size, existing garage condition, how far plumbing and electrical have to travel, finish grade, and permit scope. We quote every line separately so you can see exactly what drives the number. Call (844) 797-7958 for an exact quote, and remember estimates are free.
Every project is covered by our 730-Day Done Right Promise. If it’s not done right, we make it right, and that’s in writing before work starts. That’s one of the longer workmanship guarantees in the residential construction space. Call (844) 797-7958 for a free estimate and a copy of the promise.
Get a Free Estimate for Your Garage Conversion ADU in Burbank
We’ll come out, measure your garage, look at the slab, roof, panel, and drain lines, and tell you what’s realistic before you spend a dollar on plans. You get a written, line-item estimate with fixed pricing, plus our 730-Day Done Right Promise on the finished unit. Our technicians have up to 12 years of experience, they’re background-checked, and calls are answered by a live person around the clock. We cover Burbank and the surrounding area. If you’re weighing a broader build, start with our Home Additions & ADU service.
Call (844) 797-7958 to schedule your free estimate. If you’re repaving the approach at the same time, homeowners often pair this with Asphalt Driveways & Resurfacing in Burbank.
Written by the team at Groundwork Construction Co.